Funding :: DALLAS :: Project 81332 Details

TIP Code: 81332
CSJ: 0918-47-082
County: DALLAS
City: RICHARDSON
Agency: DALLAS CO
Project Type: INTERSECTION IMPROVEMENT
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: CS
Limits (from): ON WEST SPRING VALLEY ROAD FROM WEATHERRED DR
Limits (to): COIT RD
Scope of Work: INTERSECTION IMPROVEMENTS, TRAFFIC SIGNAL UPGRADE, ITS, RECONSTRUCTION OF BRIDGE, AND BIKE/PEDESTRIAN IMPROVEMENTS
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $17,122,733
091847082 Engineering $985,000
091847082 Right Of Way $230,000
091847082 Utilities $70,000
091847082 Construction $15,837,733
091847082 Construction Engineering $0
091847082 Contingencies $0
091847082 Indirect Costs $0
091847082 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $4,231,919 $12,890,814 $17,122,733
2011 ENG 091847082 Local Contribution $0 $0 $0 $985,000 $985,000
2012 ROW 091847082 Local Contribution $0 $0 $0 $230,000 $230,000
2012 UTIL 091847082 Local Contribution $0 $0 $0 $70,000 $70,000
2017 CON 091847082 RTR 161 - DA1 $0 $0 $4,231,919 $1,057,980 $5,289,899
2017 CON 091847082 Local Contribution $0 $0 $0 $10,547,834 $10,547,834

RTR Project Disbursements

TIP Advances Total Expenditures
  $4,231,919 $4,230,009  
81332.00 $4,231,919 $4,230,009  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2011 ENG 091847082 06/2011 06/2011 12/2013 12/2013
2012 ROW 091847082 10/2011 10/2011 08/2015 12/2015
2012 UTIL 091847082 01/2012 01/2012 03/2018 08/2016
2017 CON 091847082 06/2016 10/2016 10/2018 09/2019

TIP 81332 Environmental Review Documents

No reports found

TIP 81332 Project Attachments

No reports found