| TIP Code: | 21027.2 |
| CSJ: | 0918-47-521 |
| County: | DALLAS |
| City: | DALLAS |
| Agency: | DALLAS |
| Project Type: | TRAFFIC SIGNAL IMPROVEMENT, ITS |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | VA |
| Limits (from): | ON FOREST LN AT NUESTRA DR & PARK CENTRAL DR; ON HILLCREST RD AT CHURCHILL WAY, NORTHAVEN RD, & MEADOW RD; |
| Limits (to): | ON MARSH LN AT NORTHAVEN RD, MERRELL RD, & CLOVER LN; ON INWOOD RD AT WILLOW LN & NORTHAVEN RD |
| Scope of Work: | CONSTRUCT 10 SIGNALS IN AREA DAMAGED BY 2019 TORNADO |
| Comments: |
Total Project Cost
| CSJ | Phase | Total Project Cost |
|---|---|---|
| Total: | $5,500,000 | |
| 091847521 | Engineering | $500,000 |
| 091847521 | Construction | $5,000,000 |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $4,000,000 | $1,500,000 | $5,500,000 | ||||
| 2023 | ENG | 091847521 | Local Contribution | $0 | $0 | $0 | $500,000 | $500,000 |
| 2025 | CON | 091847521 | RTR 121 - DA1 | $0 | $0 | $4,000,000 | $1,000,000 | $5,000,000 |
RTR Project Disbursements
| TIP | Advances | Total Expenditures | |
|---|---|---|---|
| $0 | $0 |
Status
| Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|---|
| 2023 | ENG | 091847521 | 06/2023 | 06/2023 | 11/2026 | |
| 2025 | CON | 091847521 | 06/2025 | 11/2026 |
TIP 21027.2 Environmental Review Documents
|
No reports found |
TIP 21027.2 Project Attachments
|
No reports found |