TIP Code: | 21027.1 |
CSJ: | 0918-00-407 |
County: | DALLAS |
City: | DALLAS |
Agency: | DALLAS |
Project Type: | TRAFFIC SIGNAL IMPROVEMENT, ITS |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | VA |
Limits (from): | ON WALNUT HILL LN AT WINEDALE DR, TIBBS ST, BOEDECKER ST, WALNUT GLEN TOWER, & RAMBLER; MIDWAY RD AT NORTHHAVEN DR; |
Limits (to): | ON GREENVILLE AVE AT BLACKWELL ST, PINELAND DR, & MEADOW RD; ON ROYAL LN AT GEMINI LN, BROCKBANK/DENNIS RD, & WELCH RD |
Scope of Work: | CONSTRUCT 12 SIGNALS IN THE AREA DAMAGED BY THE 2019 TORNADO |
Comments: |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $6,388,636 | |
091800407 | Engineering | $600,000 |
091800407 | Construction | $5,788,636 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $4,630,909 | $1,757,727 | $6,388,636 | ||||
2023 | ENG | 091800407 | Local Contribution | $0 | $0 | $0 | $600,000 | $600,000 |
2025 | CON | 091800407 | RTR 121 - DA1 | $0 | $0 | $4,630,909 | $1,157,727 | $5,788,636 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$0 | $0 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2023 | ENG | 091800407 | 06/2023 | 06/2023 | 11/2024 | |
2025 | CON | 091800407 | 06/2025 | 11/2026 |
TIP 21027.1 Environmental Review Documents
No reports found |
TIP 21027.1 Project Attachments
No reports found |