TIP Code: | 20261 |
CSJ: | 0918-47-064 |
County: | DALLAS |
City: | GARLAND |
Agency: | GARLAND |
Project Type: | BIKE/PEDESTRIAN |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | VA |
Limits (from): | MGR BIKEWAY FROM JUPITER & APOLLO |
Limits (to): | SOUTH CITY LIMITS AT DUCK CREEK |
Scope of Work: | CONSTRUCT BIKEWAY/TRAIL CONNECTING MESQUITE AND RICHARDSON, BRIDGE OVER DUCK CREEK, TRAIL CONNECTOR UNDER IH 30, DUCK CREEK GREENBELT, DUCK CREEK BRIDGE ADJACENT TO CENTERVILLE, ON/OFF STREET GLENBROOK/KINGSBRIDGE/APOLLO CONNECTOR, LINKS TO VELOWEB |
Comments: |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $3,620,086 | |
091847064 | Engineering | $661,798 |
091847064 | Construction | $2,958,288 |
091847064 | Construction Engineering | $0 |
091847064 | Contingencies | $0 |
091847064 | Indirect Costs | $0 |
091847064 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $2,444,000 | $1,176,086 | $3,620,086 | ||||
2012 | ENG | 091847064 | RTR 121 - DA1 | $0 | $0 | $661,798 | $0 | $661,798 |
2021 | CON | 091847064 | RTR 121 - DA2 | $0 | $0 | $1,782,202 | $611,000 | $2,393,202 |
2021 | CON | 091847064 | Local Contribution | $0 | $0 | $0 | $565,086 | $565,086 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$0 | $0 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2012 | ENG | 091847064 | 07/2012 | 07/2012 | 12/2019 | 07/2019 |
2021 | CON | 091847064 | 07/2020 | 11/2020 | 12/2021 | 12/2021 |