Funding :: DALLAS :: Project 20259 Details

TIP Code: 20259
CSJ: 1068-04-154, 1068-04-164
County: DALLAS
City: DALLAS
Agency: TXDOT-DALLAS
Project Type: NEW ROADWAY
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: IH 30
Limits (from): COCKRELL HILL ROAD
Limits (to): WESTMORELAND
Scope of Work: CONSTRUCT TWO LANE WESTBOUND FRONTAGE ROAD (PHASE 2)
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $9,093,122
106804154 Engineering $200,000
106804154 Construction $6,500,000
106804154 Construction Engineering $252,000
106804154 Contingencies $70,132
106804154 Indirect Costs $270,990
106804154 Bond Financing $0
106804164 Right Of Way $1,800,000
106804164 Construction Engineering $0
106804164 Contingencies $0
106804164 Indirect Costs $0
106804164 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $200,000 $8,300,000 $0 $8,500,000
2013 ENG 106804154 SBPE $0 $200,000 $0 $0 $200,000
2013 ROW 106804164 RTR 161 - DA1 $0 $0 $1,800,000 $0 $1,800,000
2014 CON 106804154 RTR 161 - DA1 $0 $0 $6,500,000 $0 $6,500,000

RTR Project Disbursements

CSJ Total Expenditures
  $6,480,020  
106804154 $6,318,778  
106804164 $161,241  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2013 ENG 106804154 05/2010 05/2010 06/2014 06/2014
2013 ROW 106804164 05/2013 05/2013 06/2014 06/2014
2014 CON 106804154 07/2014 07/2014 03/2017 06/2017

TIP 20259 Environmental Review Documents

No reports found