| TIP Code: | 20244 |
| CSJ: | 0918-47-030 |
| County: | DALLAS |
| City: | ADDISON |
| Agency: | ADDISON |
| Project Type: | TRAFFIC SIGNAL IMPROVEMENT, BIKE/PEDESTRIAN, ADDITION OF LANES |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | VA |
| Limits (from): | VITRUVIAN PARK TRAIL INFRASTRUCTURE PROJECT FROM ONE MILE NORTH OF SPRING VALLEY ROAD TO THE NORTH |
| Limits (to): | MARSH LANE ON THE WEST, ADDISON CITY LIMIT ON THE EAST, BROOKHAVEN COLLEGE ON THE SOUTH |
| Scope of Work: | PEDESTRIAN AMENITIES, LANDSCAPING, BIKE CONNECTION, TRAFFIC SIGNALIZATION, AND WIDEN 4 LANE UNDIVIDED TO 4 LANE DIVIDED WITH PEDESTRIAN AMENITIES ON SPRING VALLEY ROAD FROM WOODWAY TO VITRUVIAN WAY |
| Comments: |
Total Project Cost
| CSJ | Phase | Total Project Cost |
|---|---|---|
| Total: | $3,570,988 | |
| 091847030 | Engineering | $132,000 |
| 091847030 | Construction | $3,438,988 |
| 091847030 | Construction Engineering | $0 |
| 091847030 | Contingencies | $0 |
| 091847030 | Indirect Costs | $0 |
| 091847030 | Bond Financing | $0 |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $2,856,791 | $714,197 | $3,570,988 | ||||
| 2011 | ENG | 091847030 | Local Contribution | $0 | $0 | $0 | $132,000 | $132,000 |
| 2011 | CON | 091847030 | RTR 121 - East Sustainable Dev | $0 | $0 | $2,856,791 | $582,197 | $3,438,988 |
RTR Project Disbursements
| TIP | Advances | Total Expenditures | |
|---|---|---|---|
| $0 | $0 |
Status
| Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|---|
| 2011 | ENG | 091847030 | 06/2012 | 06/2012 | 07/2013 | 07/2013 |
| 2011 | CON | 091847030 | 08/2013 | 08/2013 | 08/2014 | 03/2016 |
TIP 20244 Environmental Review Documents
|
No reports found |
TIP 20244 Project Attachments
|
No reports found |