TIP Code: | 20242 |
CSJ: | 0918-47-029 |
County: | DALLAS |
City: | DALLAS |
Agency: | DALLAS |
Project Type: | BIKE/PEDESTRIAN |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | VA |
Limits (from): | EDISON/HI LINE STEMMONS/RAIL TRANSIT UNDERPASS CONNECTION FROM HI LINE DR ON WEST AND N. HOUSTON ON EAST AND NORTH |
Limits (to): | AND VICTORY DART STATION AND WICHITA STREET TO THE SOUTH |
Scope of Work: | PEDESTRIAN AMENITIES; LANDSCAPING; BIKE CONNECTION |
Comments: |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $1,438,829 | |
091847029 | Implementation | $1,438,829 |
091847029 | Construction Engineering | $0 |
091847029 | Contingencies | $0 |
091847029 | Indirect Costs | $0 |
091847029 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $1,137,141 | $284,286 | $1,421,427 | ||||
2013 | IMP | 091847029 | RTR 121 - East Sustainable Dev | $0 | $0 | $1,137,141 | $284,286 | $1,421,427 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$0 | $0 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2013 | IMP | 091847029 | 08/2013 | 04/2012 | 10/2013 | 10/2013 |