Funding :: DALLAS :: Project 20227 Details

TIP Code: 20227
CSJ: 1068-04-148
County: DALLAS
City: GRAND PRAIRIE
Agency: TXDOT-DALLAS
Project Type: NEW ROADWAY
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: IH 30
Limits (from): NW 7TH
Limits (to): BELT LINE ROAD
Scope of Work: CONSTRUCT 0 TO 2/3 LANE EASTBOUND FRONTAGE ROAD AND MODIFY RAMPS
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $13,612,018
106804148 Engineering $919,290
106804148 Right Of Way $1,000,000
106804148 Utilities $1,647,600
106804148 Construction $9,009,370
106804148 Construction Engineering $426,847
106804148 Contingencies $108,890
106804148 Indirect Costs $500,021
106804148 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $10,125,576 $2,645,394 $292,960 $512,330 $13,576,260
2008 ENG 106804148 RTR 121 - DA1 $0 $0 $292,960 $73,240 $366,200
2008 ENG 106804148 Local Contribution $0 $0 $0 $439,090 $439,090
2008 ENG 106804148 SBPE $0 $114,000 $0 $0 $114,000
2015 ROW 106804148 S102 $800,000 $200,000 $0 $0 $1,000,000
2015 UTIL 106804148 S102 $1,318,080 $329,520 $0 $0 $1,647,600
2016 CON 106804148 7 - STP-MM $8,007,496 $2,001,874 $0 $0 $10,009,370

RTR Project Disbursements

CSJ Total Expenditures
  $12,359,828  
106804142 $4,485,271  
106804145 $7,581,597  
106804148 $292,960  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2008 ENG 106804148 05/2008 05/2008 01/2016 01/2016
2015 ROW 106804148 09/2014 05/2015 05/2016 08/2017
2015 UTIL 106804148 09/2014 05/2015 05/2016 08/2017
2016 CON 106804148 01/2016 02/2016 03/2019 03/2019