Funding :: DALLAS :: Project 20136 Details

TIP Code: 20136
CSJ: 0918-45-883
County: DALLAS
City: MESQUITE
Agency: MESQUITE
Project Type: BIKE/PEDESTRIAN
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: VA
Limits (from): MESQUITE HIKE & BIKE TRAIL - PHASE 1: NORTHEAST MESQUITE CITY LIMIT TO IH 30 TO NORTHWEST DRIVE TO TXU/ONCOR EASEMENT
Limits (to): TOWN CENTRE DRIVE TO IH 635
Scope of Work: CONSTRUCT FIRST SECTION OF CITY'S MAIN HIKE AND BIKE TRAIL TO CONNECT TO REGIONAL VELOWEB IN GARLAND - PHASE 1
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $3,893,648
091845883 Engineering $390,130
091845883 Right Of Way $8,358
091845883 Utilities $28,896
091845883 Construction $3,209,955
091845883 Construction Engineering $256,309
091845883 Construction Engineering $0
091845883 Contingencies $0
091845883 Indirect Costs $0
091845883 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $3,114,918 $778,730 $3,893,648
2011 ENG 091845883 RTR 121 - DA1 $0 $0 $312,104 $78,026 $390,130
2011 ROW 091845883 RTR 121 - DA1 $0 $0 $6,686 $1,672 $8,358
2013 CON 091845883 RTR 121 - DA1 $0 $0 $2,567,964 $641,991 $3,209,955
2013 CONENG 091845883 RTR 121 - DA1 $0 $0 $205,047 $51,262 $256,309
2014 UTIL 091845883 RTR 121 - DA1 $0 $0 $23,117 $5,779 $28,896

RTR Project Disbursements

TIP Advances Total Expenditures
  $3,582,131 $3,114,918  
20136.00 $3,582,131 $3,114,918  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2011 ENG 091845883 12/2010 12/2010 12/2015 12/2015
2011 ROW 091845883 02/2011 02/2011 01/2012 01/2012
2013 CON 091845883 07/2013 07/2013 09/2015 09/2015
2013 CONENG 091845883 07/2013 07/2013 05/2015 05/2015
2014 UTIL 091845883 01/2014 01/2014 03/2014 03/2014

TIP 20136 Environmental Review Documents

No reports found

TIP 20136 Project Attachments

No reports found