| TIP Code: | 20039 |
| CSJ: | 0196-03-249 |
| County: | DALLAS |
| City: | DALLAS |
| Agency: | TXDOT-DALLAS |
| Project Type: | ADDITION OF LANES |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | IH 35E |
| Limits (from): | CROWN ROAD |
| Limits (to): | JOE FIELD ROAD |
| Scope of Work: | CONSTRUCT SOUTH BOUND FRONTAGE ROAD AND ENTRANCE AND EXIT RAMPS; 0 TO 2 FRONTAGE ROADS |
| Comments: |
Total Project Cost
| CSJ | Phase | Total Project Cost |
|---|---|---|
| Total: | $2,920,320 | |
| 019603249 | Construction | $2,920,320 |
| 019603249 | Construction Engineering | $0 |
| 019603249 | Contingencies | $0 |
| 019603249 | Indirect Costs | $0 |
| 019603249 | Bond Financing | $0 |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $2,784,994 | $0 | $2,784,994 | ||||
| 2009 | CON | 019603249 | RTR 121 - DA1 | $0 | $0 | $2,784,994 | $0 | $2,784,994 |
RTR Project Disbursements
| CSJ | Total Expenditures | |
|---|---|---|
| $2,525,365 | ||
| 019603249 | $2,525,365 |
Status
| Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|---|
| 2009 | CON | 019603249 | 05/2009 | 05/2009 | 10/2010 | 09/2010 |
TIP 20039 Environmental Review Documents
|
No reports found |