Funding :: DALLAS :: Project 11536 Details

TIP Code: 11536
CSJ: 0918-47-006
County: DALLAS
City: GRAND PRAIRIE
Agency: DALLAS CO
Project Type: ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: CS
Limits (from): CAMP WISDOM RD WEST OF CARRIER PKWY
Limits (to): FM 1382
Scope of Work: WIDEN 2 TO 4 LANE DIVIDED
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $31,099,049
091847006 Engineering $2,100,000
091847006 Construction $27,385,189
091847006 Construction Engineering $679,520
091847006 Contingencies $272,630
091847006 Indirect Costs $661,710

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $10,447,939 $19,037,250 $29,485,189
2013 ENG 091847006 Local Contribution $0 $0 $0 $2,100,000 $2,100,000
2019 CON 091847006 RTR 161 - DA1 $0 $0 $10,447,939 $2,611,985 $13,059,924
2019 CON 091847006 Local Contribution $0 $0 $0 $14,325,265 $14,325,265

RTR Project Disbursements

TIP Advances Total Expenditures
  $0 $0  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2013 ENG 091847006 03/2013 03/2013 02/2019 06/2019
2019 CON 091847006 08/2018 05/2019 11/2023 11/2023

TIP 11536 Environmental Review Documents

No reports found