| TIP Code: | 11528.2 |
| CSJ: | 0918-45-793 |
| County: | DALLAS |
| City: | GRAND PRAIRIE |
| Agency: | GRAND PRAIRIE |
| Project Type: | ADDITION OF LANES |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | CS |
| Limits (from): | ON MACARTHUR RD; FROM IH 30 |
| Limits (to): | HUNTER-FERRELL |
| Scope of Work: | WIDEN 2 TO 4 LANE URBAN DIVIDED (ULTIMATE 6 LANES) |
| Comments: |
Total Project Cost
| CSJ | Phase | Total Project Cost |
|---|---|---|
| Total: | $15,000,000 | |
| 091845793 | Engineering | $724,255 |
| 091845793 | Right Of Way | $500,000 |
| 091845793 | Construction | $13,775,745 |
| 091845793 | Construction Engineering | $0 |
| 091845793 | Contingencies | $0 |
| 091845793 | Indirect Costs | $0 |
| 091845793 | Bond Financing | $0 |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $12,000,000 | $3,000,000 | $15,000,000 | ||||
| 2006 | ENG | 091845793 | RTR 121 - DA1 | $0 | $0 | $579,404 | $144,851 | $724,255 |
| 2013 | ROW | 091845793 | RTR 121 - DA1 | $0 | $0 | $400,000 | $100,000 | $500,000 |
| 2016 | CON | 091845793 | RTR 121 - DA1 | $0 | $0 | $6,932,537 | $1,733,134 | $8,665,671 |
| 2016 | CON | 091845793 | RTR 121 - DA2 | $0 | $0 | $4,088,059 | $1,022,015 | $5,110,074 |
RTR Project Disbursements
| TIP | Advances | Total Expenditures | |
|---|---|---|---|
| $12,000,000 | $808,854 | ||
| 11528.20 | $12,000,000 | $808,854 |
Status
| Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|---|
| 2006 | ENG | 091845793 | 08/2006 | 08/2006 | 09/2013 | 09/2013 |
| 2013 | ROW | 091845793 | 08/2013 | 08/2013 | 09/2015 | 08/2015 |
| 2016 | CON | 091845793 | 08/2014 | 01/2016 | 04/2018 | 04/2018 |
TIP 11528.2 Environmental Review Documents
|
No reports found |
TIP 11528.2 Project Attachments
|
No reports found |