TIP Code: | 11018.2 |
CSJ: | 0918-45-808 |
County: | DALLAS |
City: | DALLAS |
Agency: | DALLAS |
Project Type: | BIKE/PEDESTRIAN |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | VA |
Limits (from): | KATY TRAIL FROM ELLSWORTH AVE |
Limits (to): | WORCOLA STREET IN CITY OF DALLAS |
Scope of Work: | CONSTRUCT ELEVATED PEDESTRIAN BRIDGE ON KATY TRAIL - PHASE 6 |
Comments: |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $9,281,864 | |
091845808 | Engineering | $228,110 |
091845808 | Construction | $8,100,000 |
091845808 | Construction Engineering | $290,956 |
091845808 | Contingencies | $378,243 |
091845808 | Indirect Costs | $284,555 |
091845808 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $6,480,000 | $1,848,110 | $8,328,110 | ||||
2009 | ENG | 091845808 | Local Contribution | $0 | $0 | $0 | $228,110 | $228,110 |
2016 | CON | 091845808 | RTR 121 - DA1 | $0 | $0 | $6,480,000 | $1,620,000 | $8,100,000 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$6,480,000 | $6,480,000 | ||
11018.20 | $6,480,000 | $6,480,000 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2009 | ENG | 091845808 | 03/2009 | 03/2009 | 03/2011 | 03/2011 |
2016 | CON | 091845808 | 10/2015 | 11/2015 | 10/2017 | 10/2017 |
TIP 11018.2 Environmental Review Documents
No reports found |
TIP 11018.2 Project Attachments
No reports found |