| TIP Code: | 55297 |
| CSJ: | 1310-01-050 |
| County: | DENTON |
| City: | NORTHLAKE |
| Agency: | TXDOT-DALLAS |
| Project Type: | ADDITION OF LANES, RECONSTRUCTION |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | FM 407 |
| Limits (from): | EAST OF IH 35W |
| Limits (to): | WEST OF IH 35W |
| Scope of Work: | WIDEN AND RECONSTRUCT FROM 2 LANE URBAN UNDIVIDED TO 6 LANE URBAN DIVIDED |
| Comments: | REVISE FISCAL YEAR; 20% MATCH FOR RTR FUNDING BEING COVERED BY TXDOT FUNDING ON PE, ROW, CE, AND ADMIN COSTS; INCREASE FUNDING |
Total Project Cost
| CSJ | Phase | Total Project Cost |
|---|---|---|
| Total: | $52,323,764 | |
| 131001050 | Engineering | $3,373,907 |
| 131001050 | Right Of Way | $4,762,808 |
| 131001050 | Construction | $37,675,733 |
| 131001050 | Construction Engineering | $2,118,892 |
| 131001050 | Contingencies | $3,357,948 |
| 131001050 | Indirect Costs | $1,034,476 |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $3,810,246 | $3,850,188 | $37,675,733 | $476,281 | $45,812,448 | ||||
| 2022 | ENG | 131001050 | SW PE | $0 | $3,373,907 | $0 | $0 | $3,373,907 |
| 2023 | ROW | 131001050 | SW ROW | $3,810,246 | $476,281 | $0 | $476,281 | $4,762,808 |
| 2025 | CON | 131001050 | RTR 121 - DE1 | $0 | $0 | $37,675,733 | $0 | $37,675,733 |
RTR Project Disbursements
| CSJ | Total Expenditures | |
|---|---|---|
| $0 |
Status
| Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|---|
| 2022 | ENG | 131001050 | 05/2022 | 05/2022 | 08/2032 | |
| 2023 | ROW | 131001050 | 03/2023 | 03/2023 | 08/2032 | |
| 2025 | CON | 131001050 | 05/2025 | 05/2028 |