Funding :: DENTON :: Project 55275 Details

TIP Code: 55275
CSJ: 0364-03-101
County: DENTON
City: LEWISVILLE
Agency: TXDOT-DALLAS
Project Type: INTERSECTION IMPROVEMENT
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: BUS 121H
Limits (from): NORTH OF IH 35E
Limits (to): NORTH OF NORTHWOOD MOBILE HOME PARK
Scope of Work: CONSTRUCT INTERSECTION IMPROVEMENTS
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $19,063,655
036403101 Engineering $300,000
036403101 Right Of Way $13,000,000
036403101 Construction $5,311,527
036403101 Construction Engineering $241,010
036403101 Contingencies $124,617
036403101 Indirect Costs $86,501

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $10,400,000 $300,000 $5,311,527 $2,600,000 $18,611,527
2020 ENG 036403101 SW PE $0 $300,000 $0 $0 $300,000
2021 ROW 036403101 SW ROW $10,400,000 $0 $0 $2,600,000 $13,000,000
2025 CON 036403101 RTR 121 - DE1 $0 $0 $5,311,527 $0 $5,311,527

RTR Project Disbursements

CSJ Total Expenditures
  $0  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2020 ENG 036403101 06/2020 06/2020 07/2024
2021 ROW 036403101 05/2021 05/2021 07/2024
2025 CON 036403101 07/2024 08/2028

TIP 55275 Environmental Review Documents

No reports found

TIP 55275 Project Attachments

No reports found