| TIP Code: | 55039 |
| CSJ: | 2679-02-011 |
| County: | COLLIN |
| City: | LUCAS |
| Agency: | TXDOT-DALLAS |
| Project Type: | ADDITION OF LANES |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | FM 2514 |
| Limits (from): | WEST OF FM 1378 |
| Limits (to): | FM 1378 |
| Scope of Work: | RECONSTRUCT 2 LANE RURAL TO 4 LANE URBAN (ULTIMATE 6 LANE URBAN DIVIDED) |
| Comments: |
Total Project Cost
| CSJ | Phase | Total Project Cost |
|---|---|---|
| Total: | $2,451,470 | |
| 267902011 | Engineering | $40,000 |
| 267902011 | Right Of Way | $500,000 |
| 267902011 | Construction | $1,829,010 |
| 267902011 | Construction Engineering | $34,720 |
| 267902011 | Contingencies | $13,930 |
| 267902011 | Indirect Costs | $33,810 |
| 267902011 | Bond Financing | $0 |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $310,000 | $1,829,010 | $230,000 | $2,369,010 | ||||
| 2013 | ENG | 267902011 | SBPE | $0 | $40,000 | $0 | $0 | $40,000 |
| 2013 | ROW | 267902011 | Local Contribution | $0 | $0 | $0 | $200,000 | $200,000 |
| 2013 | ROW | 267902011 | S102 | $0 | $270,000 | $0 | $30,000 | $300,000 |
| 2015 | CON | 267902011 | RTR 121 - CC2 | $0 | $0 | $1,829,010 | $0 | $1,829,010 |
RTR Project Disbursements
| CSJ | Total Expenditures | |
|---|---|---|
| $1,739,955 | ||
| 267902011 | $1,739,955 |
Status
| Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|---|
| 2013 | ENG | 267902011 | 08/2013 | 08/2013 | 09/2014 | 03/2015 |
| 2013 | ROW | 267902011 | 08/2013 | 08/2013 | 01/2016 | 01/2016 |
| 2015 | CON | 267902011 | 08/2013 | 03/2015 | 02/2018 | 06/2018 |