Funding :: COLLIN :: Project 53114 Details

TIP Code: 53114
CSJ: 0047-14-067
County: COLLIN
City: MCKINNEY
Agency: TXDOT-DALLAS
Project Type: ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: US 75
Limits (from): SOUTH OF BLOOMDALE
Limits (to): TELEPHONE ROAD (CR 275)
Scope of Work: RECONSTRUCT AND WIDEN 4 LANES TO 8 LANES AND 3 LANE FRONTAGE ROADS EACH DIRECTION
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $91,493,312
004714067 Engineering $5,600,000
004714067 Construction $70,600,000
004714067 Construction Engineering $4,198,896
004714067 Contingencies $6,531,616
004714067 Indirect Costs $4,562,800
004714067 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $76,600,000 $600,000 $77,200,000
2011 ENG 004714067 RTR 121 - CC1 $0 $0 $5,000,000 $600,000 $5,600,000
2012 CON 004714067 RTR 121 - CC1 $0 $0 $71,600,000 $0 $71,600,000

RTR Project Disbursements

CSJ Total Expenditures
  $75,222,717  
004714067 $75,222,717  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2011 ENG 004714067 06/2000 06/2000 12/2011 12/2011
2012 CON 004714067 12/2011 12/2011 05/2016 02/2016