TIP Code: | 25090 |
CSJ: | 0918-00-366 |
County: | VARIOUS |
City: | VARIOUS |
Agency: | NCTCOG |
Project Type: | VEHICLE TECHNOLOGY, TRANSPORTATION SYSTEM MGMT/OPERATIONS |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | VA |
Limits (from): | ON US 75 FROM DALLAS COUNTY LINE TO SH 121 |
Limits (to): | TECHNOLOGY OR OTHER CONSTRAINED CORRIDORS; COULD BE EXPANDED TO OTHER CORRIDORS IN THE FUTURE |
Scope of Work: | GOCARMA DEMONSTRATION OF SMARTPHONE-BASED ALTERNATIVE TO CURRENT GAS TAX STRUCTURE |
Comments: |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $10,000,000 | |
091800366 | Implementation | $10,000,000 |
091800366 | Construction Engineering | $0 |
091800366 | Contingencies | $0 |
091800366 | Indirect Costs | $0 |
091800366 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$5,000,000 | $0 | $925,000 | $4,075,000 | $10,000,000 | ||||
2023 | IMP | 091800366 | RTR 121 - DA1 | $0 | $0 | $925,000 | $0 | $925,000 |
2023 | IMP | 091800366 | 10 - MISCELLANEOUS | $5,000,000 | $0 | $0 | $0 | $5,000,000 |
2023 | IMP | 091800366 | Local Contribution | $0 | $0 | $0 | $4,075,000 | $4,075,000 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$0 | $0 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2023 | IMP | 091800366 | 06/2022 | 12/2022 | 12/2024 |
TIP 25090 Environmental Review Documents
No reports found |
TIP 25090 Project Attachments
No reports found |