Funding :: VARIOUS :: Project 20299 Details

TIP Code: 20299
CSJ: 0918-00-265
County: VARIOUS
City: VARIOUS
Agency: DENTON CO
Project Type: NEW ROADWAY
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: MH
Limits (from): ON DALLAS NORTH TOLLWAY FROM FM 428
Limits (to): CR 60
Scope of Work: CONSTRUCT 0 TO 2 LANE NON-TOLLED FRONTAGE ROAD (6 LANES ULTIMATE) (DNT 4B EXTENSION)
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $32,801,000
091800265 Engineering $2,850,000
091800265 Right Of Way $1,850,000
091800265 Utilities $500,000
091800265 Construction $27,300,000
091800265 Construction Engineering $244,500
091800265 Contingencies $56,500
091800265 Indirect Costs $0
091800265 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $9,000,000 $23,500,000 $32,500,000
2011 ROW 091800265 Local Contribution $0 $0 $0 $1,850,000 $1,850,000
2011 UTIL 091800265 Local Contribution $0 $0 $0 $500,000 $500,000
2014 ENG 091800265 RTR 121 - DE1 $0 $0 $200,000 $50,000 $250,000
2014 ENG 091800265 Local Contribution $0 $0 $0 $2,600,000 $2,600,000
2020 CON 091800265 RTR 121 - DE1 $0 $0 $8,800,000 $2,200,000 $11,000,000
2020 CON 091800265 Local Contribution $0 $0 $0 $16,300,000 $16,300,000

RTR Project Disbursements

TIP Advances Total Expenditures
  $0 $0  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2011 ROW 091800265 09/2018 06/2011 04/2020 07/2020
2011 UTIL 091800265 09/2018 06/2011 07/2020 07/2020
2014 ENG 091800265 10/2014 02/2014 03/2020 07/2020
2020 CON 091800265 07/2020 08/2020 11/2022 11/2022

TIP 20299 Environmental Review Documents

No reports found

TIP 20299 Project Attachments

No reports found