| TIP Code: | 20279 |
| CSJ: | 0918-24-195 |
| County: | COLLIN |
| City: | FRISCO |
| Agency: | FRISCO |
| Project Type: | NEW ROADWAY, GRADE SEPARATION, BRIDGE |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | CS |
| Limits (from): | ON ROCKHILL ROAD FROM CR 26 |
| Limits (to): | PRESTON ROAD |
| Scope of Work: | CONSTRUCT NEW SIX-LANE DIVIDED ROADWAY INCLUDING BRIDGES OVER PARVIN BRANCH AND THE BNSF RAILROAD |
| Comments: |
Total Project Cost
| CSJ | Phase | Total Project Cost |
|---|---|---|
| Total: | $29,564,859 | |
| 091824195 | Engineering | $2,226,400 |
| 091824195 | Right Of Way | $416,967 |
| 091824195 | Construction | $26,921,492 |
| 091824195 | Construction Engineering | $0 |
| 091824195 | Contingencies | $0 |
| 091824195 | Indirect Costs | $0 |
| 091824195 | Bond Financing | $0 |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $2,953,944 | $22,918,485 | $25,872,429 | ||||
| 2008 | ENG | 091824195 | Local Contribution | $0 | $0 | $0 | $2,226,400 | $2,226,400 |
| 2013 | ROW | 091824195 | Local Contribution | $0 | $0 | $0 | $416,967 | $416,967 |
| 2013 | CON | 091824195 | RTR 121 - CC1 | $0 | $0 | $2,952,000 | $738,000 | $3,690,000 |
| 2013 | CON | 091824195 | RTR 121 - INTEREST | $0 | $0 | $1,944 | $486 | $2,430 |
| 2013 | CON | 091824195 | Local Contribution | $0 | $0 | $0 | $19,536,632 | $19,536,632 |
RTR Project Disbursements
| TIP | Advances | Total Expenditures | |
|---|---|---|---|
| $2,952,000 | $2,953,944 | ||
| 20279.00 | $2,952,000 | $2,953,944 |
Status
| Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|---|
| 2008 | ENG | 091824195 | 09/2012 | 09/2012 | 08/2013 | 08/2013 |
| 2013 | ROW | 091824195 | 08/2013 | 08/2013 | 07/2014 | 07/2014 |
| 2013 | CON | 091824195 | 08/2014 | 02/2013 | 03/2016 | 08/2017 |