| TIP Code: | 20267 |
| CSJ: | 0918-00-229 |
| County: | VARIOUS |
| City: | VARIOUS |
| Agency: | NCTCOG |
| Project Type: | SAFETY |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | VA |
| Limits (from): | M&O - SAFETY ASSURANCE REVIEWS (SAR) AT VARIOUS LOCATIONS |
| Limits (to): | |
| Scope of Work: | SAFETY ASSURANCE REVIEWS (SAR) |
| Comments: |
Total Project Cost
| CSJ | Phase | Total Project Cost |
|---|---|---|
| Total: | $210,192 | |
| 091800229 | Implementation | $210,192 |
| 091800229 | Construction Engineering | $0 |
| 091800229 | Contingencies | $0 |
| 091800229 | Indirect Costs | $0 |
| 091800229 | Bond Financing | $0 |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $210,192 | $0 | $210,192 | ||||
| 2012 | IMP | 091800229 | RTR 121 - DA1 | $0 | $0 | $210,192 | $0 | $210,192 |
RTR Project Disbursements
| TIP | Advances | Total Expenditures | |
|---|---|---|---|
| $3,550,000 | $210,192 | ||
| 20267.00 | $3,550,000 | $210,192 |
Status
| Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|---|
| 2012 | IMP | 091800229 | 05/2012 | 05/2012 | 08/2022 | 02/2019 |