| TIP Code: | 20223 |
| CSJ: | 0918-11-073 |
| County: | KAUFMAN |
| City: | SUNNYVALE |
| Agency: | DALLAS CO |
| Project Type: | SAFETY, REHABILITATION, RECONSTRUCTION |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | CS |
| Limits (from): | ON LAWSON ROAD FROM SCYENE ROAD |
| Limits (to): | US 80 |
| Scope of Work: | RECONSTRUCT EXISTING ROADWAY 2 TO 2 LANE FOR SAFETY; REHABILITATION |
| Comments: |
Total Project Cost
| CSJ | Phase | Total Project Cost |
|---|---|---|
| Total: | $3,392,015 | |
| 091811073 | Engineering | $0 |
| 091811073 | Construction | $3,392,015 |
| 091811073 | Construction Engineering | $0 |
| 091811073 | Contingencies | $0 |
| 091811073 | Indirect Costs | $0 |
| 091811073 | Bond Financing | $0 |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $3,392,015 | $0 | $3,392,015 | ||||
| 2011 | ENG | 091811073 | RTR 121 - KC1 | $0 | $0 | $0 | $0 | $0 |
| 2013 | CON | 091811073 | RTR 121 - DA1 | $0 | $0 | $2,167,015 | $0 | $2,167,015 |
| 2013 | CON | 091811073 | RTR 121 - KC1 | $0 | $0 | $1,225,000 | $0 | $1,225,000 |
RTR Project Disbursements
| TIP | Advances | Total Expenditures | |
|---|---|---|---|
| $3,392,015 | $3,392,015 | ||
| 20223.00 | $3,392,015 | $3,392,015 |
Status
| Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|---|
| 2013 | CON | 091811073 | 08/2011 | 12/2011 | 09/2016 | 07/2012 |
TIP 20223 Environmental Review Documents
|
No reports found |
TIP 20223 Project Attachments
|
No reports found |