Funding :: DENTON :: Project 20222 Details

TIP Code: 20222
CSJ: 0353-02-062, 0353-02-066
County: DENTON
City: FORT WORTH
Agency: TXDOT-DALLAS
Project Type: ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: SH 114
Limits (from): EAST OF FM 156
Limits (to): WEST OF IH 35W
Scope of Work: CONTINUOUS 3 LANE FRONTAGE ROAD (PHASE I OF FREEWAY)
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $444,768,723
035302062 Construction $27,285,972
035302062 Construction Engineering $79,734,976
035302062 Contingencies $115,172,743
035302062 Indirect Costs $8,664,534
035302062 Bond Financing $0
035302066 Right Of Way $10,338,245
035302066 Construction Engineering $79,734,976
035302066 Contingencies $115,172,743
035302066 Indirect Costs $8,664,534
035302066 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $30,099,374 $7,524,843 $37,624,217
2011 ROW 035302066 RTR 121 - DE1 $0 $0 $8,270,596 $2,067,649 $10,338,245
2011 CON 035302062 RTR 121 - DE1 $0 $0 $21,828,778 $5,457,194 $27,285,972

RTR Project Disbursements

CSJ Total Expenditures
  $29,160,376  
035302062 $20,898,838  
035302066 $8,261,538  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2011 ROW 035302066 10/2010 10/2010 10/2014 10/2014
2011 CON 035302062 10/2010 10/2010 11/2015 11/2015

TIP 20222 Environmental Review Documents

No reports found