Funding :: COLLIN :: Project 20197 Details

TIP Code: 20197
CSJ: 0047-14-068, 0047-14-071
County: COLLIN
City: MELISSA
Agency: TXDOT-DALLAS
Project Type: ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: US 75
Limits (from): TELEPHONE ROAD (CR 275)
Limits (to): NORTH OF MELISSA ROAD
Scope of Work: RECONSTRUCT AND WIDEN 4 LANE TO 6 LANES AND 2 LANE FRONTAGE ROADS EACH DIRECTION INCLUDING INTERCHANGE AT SH 121 (NORTH)
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $84,987,181
004714068 Engineering $4,839,310
004714068 Construction $66,937,162
004714068 Construction Engineering $2,267,078
004714068 Contingencies $0
004714068 Indirect Costs $0
004714068 Bond Financing $0
004714071 Right Of Way $10,943,631
004714071 Construction Engineering $0
004714071 Contingencies $0
004714071 Indirect Costs $0
004714071 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $66,937,162 $15,782,941 $0 $82,720,103
2012 ENG 004714068 RTR 121 - CC2 $0 $0 $4,839,310 $0 $4,839,310
2012 ROW 004714071 RTR 121 - CC2 $0 $0 $10,943,631 $0 $10,943,631
2012 CON 004714068 Proposition 12 V2 $0 $51,555,617 $0 $0 $51,555,617
2012 CON 004714068 TMF $0 $15,381,545 $0 $0 $15,381,545

RTR Project Disbursements

CSJ Expenditure Reimbursement Net Expenditures
  $15,782,941 $388,351 $15,394,589
004714068 $4,839,309 $262,593 $4,576,716
004714071 $10,943,631 $125,758 $10,817,873

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2012 ENG 004714068 06/2011 06/2011 08/2012 08/2012
2012 ROW 004714071 06/2011 06/2011 08/2012 08/2012
2012 CON 004714068 08/2012 08/2012 12/2017 12/2017