Funding :: ROCKWALL :: Project 20189 Details

TIP Code: 20189
CSJ: 0009-12-073
County: ROCKWALL
City: ROCKWALL
Agency: TXDOT-DALLAS
Project Type: INTERCHANGE
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: IH 30
Limits (from): AT JOHN KING BLVD INTERCHANGE
Limits (to):
Scope of Work: CONSTRUCT INTERCHANGE AT BYPASS STREET INCLUDING FRONTAGE ROADS AND RAMPS
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $23,832,484
000912073 Construction $20,826,153
000912073 Construction Engineering $881,335
000912073 Contingencies $1,273,039
000912073 Indirect Costs $851,957
000912073 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $16,082,344 $4,743,809 $20,826,153
2009 CON 000912073 RTR 121 - RC1 $0 $0 $16,082,344 $0 $16,082,344
2009 CON 000912073 Local Contribution $0 $0 $0 $4,743,809 $4,743,809

RTR Project Disbursements

CSJ Total Expenditures
  $14,822,486  
000912073 $14,822,486  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2009 CON 000912073 07/2009 07/2009 07/2012 04/2013

TIP 20189 Environmental Review Documents

No reports found

TIP 20189 Project Attachments

No reports found