| TIP Code: | 20184 |
| CSJ: | 0135-04-028 |
| County: | COLLIN |
| City: | FARMERSVILLE |
| Agency: | TXDOT-DALLAS |
| Project Type: | ADDITION OF LANES |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | US 380 |
| Limits (from): | .929 MILES WEST OF CR 557 (LAKE LAVON) |
| Limits (to): | WEST OF CR 608 (IN FARMERSVILLE) |
| Scope of Work: | WIDEN EXISTING RURAL 2 LANE HIGHWAY TO 4 LANE DIVIDED |
| Comments: |
Total Project Cost
| CSJ | Phase | Total Project Cost |
|---|---|---|
| Total: | $21,500,000 | |
| 013504028 | Construction | $21,500,000 |
| 013504028 | Construction Engineering | $0 |
| 013504028 | Contingencies | $0 |
| 013504028 | Indirect Costs | $0 |
| 013504028 | Bond Financing | $0 |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $21,500,000 | $0 | $21,500,000 | ||||
| 2009 | CON | 013504028 | RTR 121 - CC1 | $0 | $0 | $21,500,000 | $0 | $21,500,000 |
RTR Project Disbursements
| CSJ | Total Expenditures | |
|---|---|---|
| $20,514,457 | ||
| 013504028 | $20,514,457 |
Status
| Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|---|
| 2009 | CON | 013504028 | 09/2009 | 09/2009 | 11/2012 | 11/2012 |
TIP 20184 Environmental Review Documents
|
No reports found |
TIP 20184 Project Attachments
|
No reports found |