| TIP Code: | 20153 |
| CSJ: | 0902-48-847 |
| County: | TARRANT |
| City: | FORT WORTH |
| Agency: | FORT WORTH |
| Project Type: | NEW ROADWAY |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | CS |
| Limits (from): | ON RIVERSIDE DRIVE FROM STONE CREEK |
| Limits (to): | REDWOOD CREEK |
| Scope of Work: | CONSTRUCT NEW 4 LANE BRIDGE OVER FOSSIL CREEK WITH SIDEWALKS |
| Comments: |
Total Project Cost
| CSJ | Phase | Total Project Cost |
|---|---|---|
| Total: | $5,353,329 | |
| 090248847 | Construction | $4,204,471 |
| 090248847 | Construction Engineering | $322,894 |
| 090248847 | Contingencies | $419,763 |
| 090248847 | Indirect Costs | $406,201 |
| 090248847 | Bond Financing | $0 |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $2,877,180 | $719,295 | $3,596,475 | ||||
| 2013 | CON | 090248847 | RTR 161 - TC1 | $0 | $0 | $2,877,180 | $719,295 | $3,596,475 |
RTR Project Disbursements
| TIP | Advances | Total Expenditures | |
|---|---|---|---|
| $2,877,180 | $2,877,180 | ||
| 20153.00 | $2,877,180 | $2,877,180 |
Status
| Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|---|
| 2013 | CON | 090248847 | 04/2013 | 03/2013 | 03/2014 | 04/2014 |
TIP 20153 Environmental Review Documents
|
No reports found |
TIP 20153 Project Attachments
|
No reports found |