Funding :: DENTON :: Project 20146 Details

TIP Code: 20146
CSJ: 0918-46-245
County: DENTON
City: DENTON
Agency: DENTON
Project Type: ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: CS
Limits (from): ON BONNIE BRAE ROAD FROM IH 35E
Limits (to): US 377
Scope of Work: WIDEN BONNIE BRAE FROM IH 35E TO VINTAGE BLVD AND VINTAGE BLVD FROM BONNIE BRAE TO US 377 FROM 2 TO 4 LANE DIVIDED URBAN ARTERIAL
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $86,894,579
091846245 Engineering $7,429,347
091846245 Right Of Way $7,329,631
091846245 Utilities $2,883,947
091846245 Construction $69,251,654
091846245 Construction Engineering $0
091846245 Contingencies $0
091846245 Indirect Costs $0
091846245 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $46,151,352 $40,743,227 $86,894,579
2011 ENG 091846245 RTR 121 - DE1 $0 $0 $5,159,507 $1,289,877 $6,449,384
2011 ENG 091846245 Local Contribution $0 $0 $0 $979,963 $979,963
2011 ROW 091846245 RTR 121 - DE1 $0 $0 $2,857,378 $714,345 $3,571,723
2011 ROW 091846245 Local Contribution $0 $0 $0 $3,757,909 $3,757,909
2017 UTIL 091846245 RTR 121 - DE1 $0 $0 $935,887 $233,972 $1,169,859
2017 UTIL 091846245 Local Contribution $0 $0 $0 $1,714,088 $1,714,088
2017 CON 091846245 RTR 121 - DE1 $0 $0 $37,198,580 $9,299,645 $46,498,225
2017 CON 091846245 Local Contribution $0 $0 $0 $22,753,428 $22,753,428

RTR Project Disbursements

TIP Advances Total Expenditures
  $46,151,351 $31,223,855  
20146.00 $46,151,351 $31,223,855  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2011 ENG 091846245 12/2010 12/2010 12/2019 12/2019
2011 ROW 091846245 11/2012 12/2010 12/2019 12/2019
2017 UTIL 091846245 04/2016 06/2017 06/2022 06/2024
2017 CON 091846245 04/2016 06/2017 03/2026

TIP 20146 Environmental Review Documents

No reports found

TIP 20146 Project Attachments

No reports found