TIP Code: | 20131 |
CSJ: | 0918-46-236 |
County: | DENTON |
City: | LEWISVILLE |
Agency: | LEWISVILLE |
Project Type: | NEW ROADWAY, ADDITION OF LANES |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | CS |
Limits (from): | ON CORPORATE DRIVE FROM ELM FORK TRINITY RIVER BRIDGE |
Limits (to): | DGNO RR |
Scope of Work: | CONSTRUCT FOUR LANE DIVIDED ROADWAY; SEGMENT 2 |
Comments: |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $12,234,956 | |
091846236 | Engineering | $512,679 |
091846236 | Construction | $11,300,000 |
091846236 | Construction Engineering | $266,277 |
091846236 | Contingencies | $0 |
091846236 | Indirect Costs | $156,000 |
091846236 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $7,379,342 | $4,433,337 | $11,812,679 | ||||
2015 | ENG | 091846236 | RTR 121 - DE1 | $0 | $0 | $410,143 | $102,536 | $512,679 |
2024 | CON | 091846236 | RTR 121 - DE1 | $0 | $0 | $6,969,199 | $1,742,300 | $8,711,499 |
2024 | CON | 091846236 | Local Contribution | $0 | $0 | $0 | $2,588,501 | $2,588,501 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$5,379,342 | $7,376,574 | ||
20131.00 | $5,379,342 | $7,376,574 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2015 | ENG | 091846236 | 02/2014 | 01/2015 | 04/2022 | 08/2022 |
2024 | CON | 091846236 | 12/2023 | 10/2023 | 12/2026 |
TIP 20131 Environmental Review Documents
No reports found |
TIP 20131 Project Attachments
No reports found |