Funding :: DENTON :: Project 20099 Details

TIP Code: 20099
CSJ: 0918-46-234
County: DENTON
City: LITTLE ELM
Agency: LITTLE ELM
Project Type: ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: CS
Limits (from): ON WITT ROAD FROM ELDORADO PARKWAY (FM 720)
Limits (to): KING ROAD
Scope of Work: RECONSTRUCT BRIDGE OVER COTTONWOOD CREEK 2 TO 4 LANES DIVIDED URBAN
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $6,966,210
091846234 Engineering $594,880
091846234 Right Of Way $91,500
091846234 Utilities $9,035
091846234 Construction $6,270,795
091846234 Construction Engineering $0
091846234 Contingencies $0
091846234 Indirect Costs $0
091846234 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $5,572,968 $1,393,242 $6,966,210
2010 ENG 091846234 RTR 121 - DE1 $0 $0 $475,904 $118,976 $594,880
2010 ROW 091846234 RTR 121 - DE1 $0 $0 $73,200 $18,300 $91,500
2011 UTIL 091846234 RTR 121 - DE1 $0 $0 $7,228 $1,807 $9,035
2011 CON 091846234 RTR 121 - DE1 $0 $0 $5,016,636 $1,254,159 $6,270,795

RTR Project Disbursements

TIP Advances Total Expenditures
  $5,502,570 $5,575,341  
20099.00 $5,502,570 $5,575,341  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2010 ENG 091846234 02/2010 02/2010 09/2011 09/2011
2010 ROW 091846234 06/2011 06/2011 06/2011 06/2011
2011 UTIL 091846234 12/2010 12/2010 02/2013 12/2012
2011 CON 091846234 09/2009 12/2010 02/2013 12/2012