TIP Code: | 20088 |
CSJ: | 0918-24-174 |
County: | COLLIN |
City: | VARIOUS |
Agency: | NCTCOG |
Project Type: | SPECIAL STUDIES |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | CS |
Limits (from): | ON OUTER LOOP FROM DENTON COUNTY LINE |
Limits (to): | ROCKWALL COUNTY LINE |
Scope of Work: | ENVIRONMENTAL CLEARANCE FOR CONSTRUCTION OF OUTER LOOP |
Comments: |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $900,000 | |
091824174 | Environmental | $900,000 |
091824174 | Construction Engineering | $0 |
091824174 | Contingencies | $0 |
091824174 | Indirect Costs | $0 |
091824174 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $900,000 | $0 | $900,000 | ||||
2010 | ENV | 091824174 | RTR 121 - CC1 | $0 | $0 | $900,000 | $0 | $900,000 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$874,780 | $289,363 | ||
20088.00 | $874,780 | $289,363 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2010 | ENV | 091824174 | 08/2009 | 08/2009 | 09/2028 |