| TIP Code: | 20086 |
| CSJ: | 0364-04-048 |
| County: | COLLIN |
| City: | FRISCO |
| Agency: | FRISCO |
| Project Type: | INTERSECTION IMPROVEMENT |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | SH 121 |
| Limits (from): | ON SOUTHBOUND FRTG RD AT OHIO DRIVE |
| Limits (to): | |
| Scope of Work: | DESIGN AND CONSTRUCT A RIGHT TURN BAY ON THE SOUTH BOUND FRONTAGE ROAD OF SH 121 AT OHIO DRIVE |
| Comments: |
Total Project Cost
| CSJ | Phase | Total Project Cost |
|---|---|---|
| Total: | $345,128 | |
| 036404048 | Construction | $294,468 |
| 036404048 | Construction Engineering | $19,595 |
| 036404048 | Contingencies | $18,289 |
| 036404048 | Indirect Costs | $12,776 |
| 036404048 | Bond Financing | $0 |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $235,574 | $58,894 | $294,468 | ||||
| 2018 | CON | 036404048 | RTR 121 - CC1 | $0 | $0 | $235,574 | $58,894 | $294,468 |
RTR Project Disbursements
| CSJ | Total Expenditures | |
|---|---|---|
| $235,574 | ||
| 036404048 | $235,574 |
Status
| Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|---|
| 2018 | CON | 036404048 | 03/2018 | 01/2018 | 10/2019 | 10/2019 |
TIP 20086 Environmental Review Documents
|
No reports found |
TIP 20086 Project Attachments
|
No reports found |