Funding :: COLLIN :: Project 20084 Details

TIP Code: 20084
CSJ: 0047-14-053
County: COLLIN
City: VARIOUS
Agency: TXDOT-DALLAS
Project Type: ADDITION OF LANES, RECONSTRUCTION
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: US 75
Limits (from): NORTH OF CR 370
Limits (to): CR 375 (GRAYSON COUNTY LINE)
Scope of Work: RECONSTRUCT AND WIDEN FROM 4 LANE TO 6 LANE FREEWAY AND RECONSTRUCT AND WIDEN EXISTING 4 LANE CONTINUOUS FRONTAGE ROAD TO 4/6 LANE CONTINUOUS FRONTAGE ROAD
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $110,447,275
004714053 Engineering $5,476,147
004714053 Right Of Way $5,478,873
004714053 Construction $80,649,840
004714053 Construction Engineering $6,984,881
004714053 Contingencies $6,571,376
004714053 Indirect Costs $5,286,158
004714053 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $69,389,981 $22,214,879 $0 $0 $91,604,860
2005 ENG 004714053 SW PE $0 $5,476,147 $0 $0 $5,476,147
2012 ROW 004714053 SW ROW $4,870,109 $608,764 $0 $0 $5,478,873
2024 CON 004714053 12 - STRAT PRIORITY $51,023,215 $12,755,804 $0 $0 $63,779,019
2024 CON 004714053 4 - STATEWIDE CONNECTIVITY $13,496,657 $3,374,164 $0 $0 $16,870,821

RTR Project Disbursements

CSJ Total Expenditures
  $0  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2005 ENG 004714053 09/2017 01/2005 01/2024 01/2024
2012 ROW 004714053 09/2017 06/2012 09/2019 08/2016
2024 CON 004714053 01/2024 01/2024 08/2027

TIP 20084 Environmental Review Documents

No reports found

TIP 20084 Project Attachments

No reports found