TIP Code: | 20082 |
CSJ: | 3392-01-009, 3392-01-011 |
County: | COLLIN |
City: | ALLEN |
Agency: | TXDOT-DALLAS |
Project Type: | ADDITION OF LANES |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | FM 2786 |
Limits (from): | EAST OF ANGEL PKWY |
Limits (to): | FM 1378 |
Scope of Work: | RECONSTRUCT 2 LANE ROADWAY TO A 4 LANE (ULTIMATE 6) DIVIDED ROADWAY |
Comments: |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $10,513,090 | |
339201009 | Construction | $8,272,548 |
339201009 | Construction Engineering | $330,767 |
339201009 | Contingencies | $477,775 |
339201009 | Indirect Costs | $359,434 |
339201009 | Bond Financing | $0 |
339201011 | Right Of Way | $1,072,566 |
339201011 | Utilities | $0 |
339201011 | Construction Engineering | $0 |
339201011 | Contingencies | $0 |
339201011 | Indirect Costs | $0 |
339201011 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $7,737,857 | $1,607,257 | $9,345,114 | ||||
2011 | ROW | 339201011 | RTR 121 - CC1 | $0 | $0 | $965,309 | $107,257 | $1,072,566 |
2011 | UTIL | 339201011 | RTR 121 - CC2 | $0 | $0 | $0 | $0 | $0 |
2015 | CON | 339201009 | RTR 121 - CC1 | $0 | $0 | $6,772,548 | $0 | $6,772,548 |
2015 | CON | 339201009 | Local Contribution | $0 | $0 | $0 | $1,500,000 | $1,500,000 |
RTR Project Disbursements
CSJ | Total Expenditures | |
---|---|---|
$7,439,873 | ||
339201009 | $6,520,963 | |
339201011 | $918,910 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2011 | ROW | 339201011 | 01/2011 | 01/2011 | 12/2014 | 12/2013 |
2015 | CON | 339201009 | 12/2014 | 12/2014 | 12/2019 | 08/2019 |