TIP Code: | 20069 |
CSJ: | 0918-24-170 |
County: | COLLIN |
City: | PLANO |
Agency: | DART |
Project Type: | PARK & RIDE/RAIL STATION |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | VA |
Limits (from): | NORTHWEST PLANO PARK AND RIDE LOT FROM WEST SIDE OF THE DALLAS NORTH TOLLWAY |
Limits (to): | BETWEEN TENNYSON PARKWAY AND SPRING CREEK PARKWAY |
Scope of Work: | CONSTRUCT 544 SPACES (ULTIMATELY 716 SPACES) |
Comments: | PHASE 1 PNR SPACES COMPLETED 01/2013; PHASE 2 ITS WORK TO START 10/2015, EST COMPLETION IN 10/2016; PHASE 3 ADDITIONAL WORK AT LOCATION 12/15 EST COMPLETION IN 12/2016 |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $12,700,000 | |
091824170 | Engineering | $2,250,000 |
091824170 | Construction | $10,450,000 |
091824170 | Construction Engineering | $0 |
091824170 | Contingencies | $0 |
091824170 | Indirect Costs | $0 |
091824170 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $8,500,000 | $4,200,000 | $12,700,000 | ||||
2011 | ENG | 091824170 | RTR 121 - CC1 | $0 | $0 | $1,500,000 | $750,000 | $2,250,000 |
2014 | CON | 091824170 | RTR 121 - CC1 | $0 | $0 | $7,000,000 | $3,450,000 | $10,450,000 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$8,500,000 | $31,456,494 | ||
20069.00 | $8,500,000 | $31,456,494 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2011 | ENG | 091824170 | 01/2011 | 01/2011 | 08/2012 | 08/2012 |
2014 | CON | 091824170 | 01/2014 | 01/2014 | 09/2023 |
TIP 20069 Environmental Review Documents
No reports found |
TIP 20069 Project Attachments
No reports found |