TIP Code: | 20058 |
CSJ: | 0918-24-156 |
County: | COLLIN |
City: | PLANO |
Agency: | PLANO |
Project Type: | INTERSECTION IMPROVEMENT |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | CS |
Limits (from): | PARKER ROAD |
Limits (to): | AT COIT ROAD AND ALMA ROAD |
Scope of Work: | ADD DUAL LEFT AND RIGHT TURN LANES |
Comments: |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $1,936,084 | |
091824156 | Engineering | $189,280 |
091824156 | Right Of Way | $112,486 |
091824156 | Construction | $1,433,076 |
091824156 | Construction Engineering | $0 |
091824156 | Contingencies | $201,242 |
091824156 | Indirect Costs | $0 |
091824156 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $1,387,874 | $346,968 | $1,734,842 | ||||
2010 | ENG | 091824156 | RTR 121 - CC1 | $0 | $0 | $151,424 | $37,856 | $189,280 |
2011 | ROW | 091824156 | RTR 121 - CC1 | $0 | $0 | $89,989 | $22,497 | $112,486 |
2021 | CON | 091824156 | RTR 121 - CC1 | $0 | $0 | $1,146,461 | $286,615 | $1,433,076 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$1,387,874 | $1,787,299 | ||
20058.00 | $1,387,874 | $1,787,299 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2010 | ENG | 091824156 | 05/2012 | 03/2012 | 04/2018 | 10/2019 |
2011 | ROW | 091824156 | 01/2014 | 01/2014 | 09/2015 | 09/2016 |
2021 | CON | 091824156 | 07/2020 | 11/2020 | 10/2024 |
TIP 20058 Environmental Review Documents
No reports found |
TIP 20058 Project Attachments
No reports found |