TIP Code: | 20054 |
CSJ: | 0918-24-161 |
County: | COLLIN |
City: | VARIOUS |
Agency: | NCTCOG |
Project Type: | RAIL TRANSIT |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | VA |
Limits (from): | COTTONBELT PASSENGER RAIL CORRIDOR (COLLIN COUNTY SECTION) FROM DFWIA |
Limits (to): | NORTH CENTRAL/RED LINE |
Scope of Work: | PROVIDE A KEY EAST-WEST PASSENGER RAIL LINK ACROSS THE NORTHERN PART OF THE DART SERVICE AREA |
Comments: | ALL FUNDS TRANSFERRED; IS PROJECT COMPLETE? |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $1,583,333 | |
091824161 | Implementation | $1,583,333 |
091824161 | Construction Engineering | $0 |
091824161 | Contingencies | $0 |
091824161 | Indirect Costs | $0 |
091824161 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $1,000,000 | $0 | $1,000,000 | ||||
2010 | IMP | 091824161 | RTR 121 - CC1 | $0 | $0 | $666,667 | $0 | $666,667 |
2011 | IMP | 091824161 | RTR 121 - CC1 | $0 | $0 | $333,333 | $0 | $333,333 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$1,000,000 | $1,000,000 | ||
20054.00 | $1,000,000 | $1,000,000 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2010 | IMP | 091824161 | 08/2009 | 08/2009 | 08/2015 | 09/2019 |
2011 | IMP | 091824161 | 08/2009 | 08/2009 | 09/2019 | 09/2019 |
TIP 20054 Environmental Review Documents
No reports found |
TIP 20054 Project Attachments
No reports found |