TIP Code: | 20025 |
CSJ: | 2681-01-012, 2681-01-018 |
County: | DENTON |
City: | CORINTH |
Agency: | TXDOT-DALLAS |
Project Type: | NEW ROADWAY |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | FM 2499 |
Limits (from): | FM 2181 NORTH |
Limits (to): | IH 35E |
Scope of Work: | CONSTRUCT 6 LANE DIVIDED URBAN FACILITY ON NEW LOCATION (SEGMENT 5) |
Comments: |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $52,011,598 | |
268101012 | Engineering | $3,400,000 |
268101012 | Construction | $34,857,000 |
268101012 | Construction Engineering | $1,707,993 |
268101012 | Contingencies | $435,713 |
268101012 | Indirect Costs | $1,683,593 |
268101012 | Bond Financing | $0 |
268101018 | Right Of Way | $6,100,000 |
268101018 | Construction Engineering | $1,707,993 |
268101018 | Contingencies | $435,713 |
268101018 | Indirect Costs | $1,683,593 |
268101018 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $900,000 | $46,502,832 | $2,500,000 | $49,902,832 | ||||
2006 | ENG | 268101012 | Local Contribution | $0 | $0 | $0 | $2,500,000 | $2,500,000 |
2006 | ENG | 268101012 | SBPE | $0 | $900,000 | $0 | $0 | $900,000 |
2006 | ROW | 268101018 | RTR 121 - DE1 | $0 | $0 | $4,814,867 | $0 | $4,814,867 |
2014 | CON | 268101012 | RTR 121 - DE1 | $0 | $0 | $41,687,965 | $0 | $41,687,965 |
RTR Project Disbursements
CSJ | Total Expenditures | |
---|---|---|
$46,296,853 | ||
268101012 | $40,395,053 | |
268101018 | $5,901,800 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2006 | ENG | 268101012 | 01/2006 | 01/2006 | 06/2014 | 06/2014 |
2006 | ROW | 268101018 | 01/2006 | 01/2006 | 03/2014 | 03/2014 |
2014 | CON | 268101012 | 07/2014 | 07/2014 | 11/2018 | 11/2018 |
TIP 20025 Environmental Review Documents
No reports found |
TIP 20025 Project Attachments
No reports found |