Funding :: COLLIN :: Project 20008 Details

TIP Code: 20008
CSJ: 0135-12-025, 0135-12-027
County: COLLIN
City: FRISCO
Agency: TXDOT-DALLAS
Project Type: ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: FM 3537
Limits (from): SH 289
Limits (to): FM 2478
Scope of Work: WIDEN 2 LANE RURAL TO 6 LANE DIVIDED URBAN HIGHWAY
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $44,396,327
013512025 Engineering $786,550
013512025 Construction $25,425,353
013512025 Construction Engineering $1,098,573
013512025 Contingencies $1,586,828
013512025 Indirect Costs $1,193,783
013512025 Bond Financing $0
013512027 Right Of Way $3,926,056
013512027 Utilities $6,500,000
013512027 Construction Engineering $1,098,573
013512027 Contingencies $1,586,828
013512027 Indirect Costs $1,193,783
013512027 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $33,920,953 $750,906 $34,671,859
2010 ENG 013512025 RTR 121 - CC1 $0 $0 $822,425 $0 $822,425
2011 ROW 013512027 RTR 121 - CC1 $0 $0 $6,758,150 $750,906 $7,509,056
2011 UTIL 013512027 RTR 121 - CC1 $0 $0 $915,025 $0 $915,025
2011 CON 013512025 RTR 121 - CC1 $0 $0 $7,425,353 $0 $7,425,353
2011 CON 013512025 RTR 121 - DE1 $0 $0 $18,000,000 $0 $18,000,000

RTR Project Disbursements

CSJ Total Expenditures
  $32,186,898  
013512025 $25,089,516  
013512027 $7,097,382  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2010 ENG 013512025 03/2000 03/2000 06/2011 06/2011
2011 ROW 013512027 01/2011 01/2011 06/2011 06/2011
2011 UTIL 013512027 01/2011 01/2011 06/2011 06/2011
2011 CON 013512025 06/2011 06/2011 09/2016 09/2016

TIP 20008 Environmental Review Documents

No reports found

TIP 20008 Project Attachments

No reports found