| TIP Code: | 20002 |
| CSJ: | 2980-01-008 |
| County: | DENTON |
| City: | FRISCO |
| Agency: | TXDOT-DALLAS |
| Project Type: | ADDITION OF LANES |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | FM 2934 |
| Limits (from): | ON FM 2934/ELDORADO PARKWAY FROM FM 423 |
| Limits (to): | DALLAS NORTH TOLLWAY/COLLIN COUNTY LINE |
| Scope of Work: | WIDEN EXISTING 2 LANE RURAL TO 6 LANE DIVIDED URBAN ROADWAY |
| Comments: |
Total Project Cost
| CSJ | Phase | Total Project Cost |
|---|---|---|
| Total: | $23,211,560 | |
| 298001008 | Construction | $23,211,560 |
| 298001008 | Construction Engineering | $0 |
| 298001008 | Contingencies | $0 |
| 298001008 | Indirect Costs | $0 |
| 298001008 | Bond Financing | $0 |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $21,184,314 | $0 | $21,184,314 | ||||
| 2009 | CON | 298001008 | RTR 121 - DE1 | $0 | $0 | $21,184,314 | $0 | $21,184,314 |
RTR Project Disbursements
| CSJ | Total Expenditures | |
|---|---|---|
| $20,575,417 | ||
| 298001008 | $20,575,417 |
Status
| Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|---|
| 2009 | CON | 298001008 | 09/2008 | 09/2008 | 04/2010 | 04/2010 |