TIP Code: | 14060 |
CSJ: | 0918-24-258 |
County: | COLLIN |
City: | MCKINNEY |
Agency: | MCKINNEY |
Project Type: | INTERSECTION IMPROVEMENT, BIKE/PEDESTRIAN, RECONSTRUCTION |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | CS |
Limits (from): | E LOUISIANA STREET FROM SH 5 |
Limits (to): | THROCKMORTON ST |
Scope of Work: | RECONSTRUCT FROM 2 TO 2 LANES INCLUDING ON-STREET PARKING, ROUNDABOUT AT THE INTERSECTION OF EAST LOUISIANA AND GREENVILLE ST, AND SIDEWALK IMPROVEMENTS |
Comments: |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $7,380,450 | |
091824258 | Engineering | $712,989 |
091824258 | Construction | $6,190,000 |
091824258 | Construction Engineering | $134,127 |
091824258 | Contingencies | $232,200 |
091824258 | Indirect Costs | $111,134 |
091824258 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $4,595,000 | $2,307,989 | $6,902,989 | ||||
2021 | ENG | 091824258 | Local Contribution | $0 | $0 | $0 | $712,989 | $712,989 |
2022 | CON | 091824258 | RTR 121 - CC2 | $0 | $0 | $4,595,000 | $0 | $4,595,000 |
2022 | CON | 091824258 | Local Contribution | $0 | $0 | $0 | $1,595,000 | $1,595,000 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$4,138,518 | $3,968,152 | ||
14060.00 | $4,138,518 | $3,968,152 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2021 | ENG | 091824258 | 09/2020 | 10/2020 | 12/2021 | 01/2022 |
2022 | CON | 091824258 | 02/2022 | 06/2022 | 06/2024 |
TIP 14060 Environmental Review Documents
No reports found |
TIP 14060 Project Attachments
No reports found |