TIP Code: | 11929 |
CSJ: | 0902-90-249 |
County: | TARRANT |
City: | SOUTHLAKE |
Agency: | SOUTHLAKE |
Project Type: | BRIDGE, BIKE/PEDESTRIAN, RECONSTRUCTION |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | CS |
Limits (from): | N WHITE CHAPEL BLVD FROM NORTH OF BLUESTEM DR |
Limits (to): | SOUTH OF WINGATE LN |
Scope of Work: | RECONSTRUCT BRIDGE AND ROADWAY APPROACHES, AND ADD SIDEWALKS DUE TO FLOODING |
Comments: |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $7,268,063 | |
090290249 | Engineering | $710,000 |
090290249 | Construction | $5,947,490 |
090290249 | Construction Engineering | $249,332 |
090290249 | Contingencies | $208,050 |
090290249 | Indirect Costs | $153,191 |
090290249 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $4,757,992 | $1,899,498 | $6,657,490 | ||||
2022 | ENG | 090290249 | Local Contribution | $0 | $0 | $0 | $710,000 | $710,000 |
2023 | CON | 090290249 | RTR 121 - DE1 | $0 | $0 | $4,757,992 | $1,189,498 | $5,947,490 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$3,491,520 | $3,956,242 | ||
11929.00 | $3,491,520 | $3,956,242 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2022 | ENG | 090290249 | 09/2021 | 09/2021 | 03/2022 | 04/2023 |
2023 | CON | 090290249 | 06/2022 | 08/2023 | 08/2025 |
TIP 11929 Environmental Review Documents
No reports found |