Funding :: DENTON :: Project 11432 Details

TIP Code: 11432
CSJ: 2054-02-016, 2054-02-018
County: DENTON
City: CORINTH
Agency: DENTON CO
Project Type: ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: FM 2181
Limits (from): WEST OF FM 2499 (BARREL STRAP RD)
Limits (to): WEST FRONTAGE ROAD OF IH 35E
Scope of Work: WIDEN 2 LANE RURAL TO 6 LANE DIVIDED URBAN
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $50,119,715
205402016 Engineering $1,956,693
205402016 Construction $25,260,000
205402016 Construction Engineering $1,333,975
205402016 Contingencies $2,667,950
205402016 Indirect Costs $1,449,586
205402016 Bond Financing $0
205402018 Right Of Way $11,000,000
205402018 Utilities $1,000,000
205402018 Construction Engineering $1,333,975
205402018 Contingencies $2,667,950
205402018 Indirect Costs $1,449,586
205402018 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $22,208,000 $5,052,000 $10,640,000 $2,956,693 $40,856,693
1999 ENG 205402016 Local Contribution $0 $0 $0 $1,856,693 $1,856,693
2008 ENG 205402016 RTR 121 - DE1 $0 $0 $640,000 $0 $640,000
2011 ROW 205402018 RTR 121 - DE1 $0 $0 $9,500,000 $1,100,000 $10,600,000
2012 UTIL 205402018 RTR 121 - DE1 $0 $0 $500,000 $0 $500,000
2013 CON 205402016 12 (425) $1,488,000 $372,000 $0 $0 $1,860,000
2013 CON 205402016 7 - STP-MM $20,720,000 $4,680,000 $0 $0 $25,400,000

RTR Project Disbursements

CSJ Total Expenditures
  $10,803,740  
205402016 $495,345  
205402018 $10,308,395  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
1999 ENG 205402016 12/1999 12/1999 12/2012 12/2012
2008 ENG 205402016 12/1999 12/1999 12/2012 12/2012
2011 ROW 205402018 04/2011 04/2011 05/2012 05/2012
2012 UTIL 205402018 04/2012 04/2012 07/2013 07/2013
2013 CON 205402016 05/2013 05/2013 10/2016 10/2016

TIP 11432 Environmental Review Documents

No reports found

TIP 11432 Project Attachments