| TIP Code: | 11217.2 |
| CSJ: | 0918-46-298 |
| County: | DENTON |
| City: | DENTON |
| Agency: | DENTON |
| Project Type: | ADDITION OF LANES |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | CS |
| Limits (from): | ON MCKINNEY ST (OLD FM 426) FROM |
| Limits (to): | 1.4 MI W SL 288 TO 1.1 MI E SL 288 |
| Scope of Work: | WIDEN 2 LANE ROADWAY TO 4 LANE DIVIDED URBAN |
| Comments: |
Total Project Cost
| CSJ | Phase | Total Project Cost |
|---|---|---|
| Total: | $18,267,303 | |
| 091846298 | Utilities | $1,000,000 |
| 091846298 | Construction | $17,267,303 |
| 091846298 | Construction Engineering | $0 |
| 091846298 | Contingencies | $0 |
| 091846298 | Indirect Costs | $0 |
| 091846298 | Bond Financing | $0 |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $18,267,303 | $0 | $18,267,303 | ||||
| 2017 | UTIL | 091846298 | RTR 121 - DE1 | $0 | $0 | $1,000,000 | $0 | $1,000,000 |
| 2020 | CON | 091846298 | RTR 121 - DE1 | $0 | $0 | $17,267,303 | $0 | $17,267,303 |
RTR Project Disbursements
| TIP | Advances | Total Expenditures | |
|---|---|---|---|
| $18,342,382 | $16,789,563 | ||
| 11217.20 | $18,342,382 | $16,789,563 |
Status
| Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|---|
| 2017 | UTIL | 091846298 | 09/2017 | 02/2017 | 04/2019 | 09/2019 |
| 2020 | CON | 091846298 | 12/2019 | 10/2019 | 03/2022 | 07/2023 |
TIP 11217.2 Environmental Review Documents
|
No reports found |
TIP 11217.2 Project Attachments
|
No reports found |