Funding :: DALLAS :: Project 2310.1 Details

TIP Code: 2310.1
CSJ: 0918-47-057
County: DALLAS
City: DALLAS
Agency: DALLAS CO
Project Type: BIKE/PEDESTRIAN, ADDITION OF LANES, RECONSTRUCTION
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: CS
Limits (from): DENTON DRIVE FROM SOUTH OF WALNUT HILL LANE
Limits (to): NORTH OF ROYAL LN
Scope of Work: RECONSTRUCT DENTON DR FROM 2 LN UNDIVIDED RURAL INTO 3 LN URBAN TRANSIT ORIENTED ROADWAY WITH CENTER TURN LN, BIKE LN, SIDEWALKS, AND SIDEWALK CONNECTION TO HARRY HINES BLVD ALONG BOTH WALNUT HILL LN AND ROYAL LN CONNECTING DART LRT STATION
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $15,550,366
091847057 Engineering $800,366
091847057 Right Of Way $750,000
091847057 Utilities $1,000,000
091847057 Construction $13,000,000
091847057 Construction Engineering $0
091847057 Contingencies $0
091847057 Indirect Costs $0
091847057 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $550,000 $15,000,366 $15,550,366
2012 ENG 091847057 RTR 121 - DA2 $0 $0 $550,000 $137,866 $687,866
2012 ENG 091847057 Local Contribution $0 $0 $0 $112,500 $112,500
2014 ROW 091847057 Local Contribution $0 $0 $0 $750,000 $750,000
2016 UTIL 091847057 Local Contribution $0 $0 $0 $1,000,000 $1,000,000
2018 CON 091847057 Local Contribution $0 $0 $0 $13,000,000 $13,000,000

RTR Project Disbursements

TIP Advances Total Expenditures
  $550,000 $550,000  
2310.10 $550,000 $550,000  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2012 ENG 091847057 10/2011 10/2011 05/2016 05/2016
2014 ROW 091847057 11/2013 11/2013 08/2016 06/2017
2016 UTIL 091847057 08/2016 08/2016 10/2017 11/2017
2018 CON 091847057 11/2017 01/2018 04/2021 06/2021