TIP Code: | 20215 |
CSJ: | 0081-04-035 |
County: | DENTON |
City: | DENTON |
Agency: | TXDOT-DALLAS |
Project Type: | GRADE SEPARATION |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | US 377 |
Limits (from): | AT UNION PACIFIC RAILROAD OVERPASS |
Limits (to): | (0.4 MILES SOUTH OF IH 35E) |
Scope of Work: | REPLACE WITH 6 LANE OVERPASS (2 TO 6 LANES) |
Comments: |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $11,970,192 | |
008104035 | Engineering | $500,000 |
008104035 | Construction | $10,207,203 |
008104035 | Construction Engineering | $358,577 |
008104035 | Contingencies | $517,945 |
008104035 | Indirect Costs | $386,467 |
008104035 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$1,200,000 | $11,779,796 | $0 | $0 | $12,979,796 | ||||
2005 | ENG | 008104035 | SBPE | $0 | $500,000 | $0 | $0 | $500,000 |
2018 | CON | 008104035 | 1 - PREV MAINT | $0 | $4,690,906 | $0 | $0 | $4,690,906 |
2018 | CON | 008104035 | 2M - METRO CORR | $1,200,000 | $300,000 | $0 | $0 | $1,500,000 |
2018 | CON | 008104035 | Cat 2M - Proposition 1 | $0 | $2,269,248 | $0 | $0 | $2,269,248 |
2018 | CON | 008104035 | Cat 4 - Proposition 1 | $0 | $4,019,642 | $0 | $0 | $4,019,642 |
RTR Project Disbursements
CSJ | Total Expenditures | |
---|---|---|
$0 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2005 | ENG | 008104035 | 07/2005 | 07/2005 | 05/2018 | 07/2018 |
2018 | CON | 008104035 | 07/2018 | 07/2018 | 07/2021 | 05/2021 |
TIP 20215 Environmental Review Documents
No reports found |
TIP 20215 Project Attachments
No reports found |