TIP Code: | 11726.3 |
CSJ: | 0918-45-885 |
County: | DALLAS |
City: | DALLAS |
Agency: | DALLAS |
Project Type: | INTERSECTION IMPROVEMENT, BIKE/PEDESTRIAN, ADDITION OF LANES, RECONSTRUCTION |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | CS |
Limits (from): | ON RIVERFRONT BOULEVARD FROM UP RR |
Limits (to): | NORTH OF CONTINENTAL AVENUE |
Scope of Work: | RECONSTRUCT 6 LANE TO 6 LANE WITH BIKE/PEDESTRIAN IMPROVEMENTS, AND INTERSECTION IMPROVEMENTS |
Comments: |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $13,862,027 | |
091845885 | Engineering | $1,350,000 |
091845885 | Construction | $8,550,000 |
091845885 | Construction Engineering | $1,897,977 |
091845885 | Contingencies | $0 |
091845885 | Indirect Costs | $2,064,050 |
091845885 | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $6,840,000 | $3,060,000 | $9,900,000 | ||||
2009 | ENG | 091845885 | Local Contribution | $0 | $0 | $0 | $1,350,000 | $1,350,000 |
2014 | CON | 091845885 | RTR 121 - DA1 | $0 | $0 | $6,840,000 | $1,710,000 | $8,550,000 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$0 | $0 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2009 | ENG | 091845885 | 04/2009 | 06/2009 | 08/2014 | 08/2014 |
2014 | CON | 091845885 | 04/2014 | 08/2014 | 12/2020 | 06/2018 |
TIP 11726.3 Environmental Review Documents
No reports found |
TIP 11726.3 Project Attachments