Funding :: DALLAS :: Project 53123 Details

TIP Code: 53123
CSJ: 0196-03-138, 0196-03-248
County: DALLAS
City: CARROLLTON
Agency: TXDOT-DALLAS
Project Type: ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: IH 35E
Limits (from): IH 635
Limits (to): PGBT
Scope of Work: RECONSTRUCT 6 LANE TO 6 MAINLANES, 2 CONCURRENT TO 2 LANE REVERSIBLE HOV/MANAGED, 2/6 TO 2/6 LANE CONTINUOUS FRONTAGE ROADS, AND INTERCHANGE AT IH 35E AND IH 635 (PHASED IMPLEMENTATION OF THE IH 35E CORRIDOR)
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $268,183,876
019603138 Right Of Way $45,709,858
019603138 Construction $172,208,000
019603138 Construction Engineering $4,373,100
019603138 Contingencies $183,060
019603138 Indirect Costs $0
019603138 Bond Financing $0
019603248 Right Of Way $45,709,858
019603248 Construction Engineering $0
019603248 Contingencies $0
019603248 Indirect Costs $0
019603248 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $112,566,400 $119,561,316 $31,500,000 $0 $263,627,716
2013 ROW 019603138 SW ROW $0 $45,709,858 $0 $0 $45,709,858
2013 ROW 019603248 SW ROW $0 $45,709,858 $0 $0 $45,709,858
2013 CON 019603138 RTR 121 - DA1 $0 $0 $31,500,000 $0 $31,500,000
2013 CON 019603138 12 - STRAT PRIORITY $31,811,295 $0 $0 $0 $31,811,295
2013 CON 019603138 2M - METRO CORR $45,148,705 $11,287,176 $0 $0 $56,435,881
2013 CON 019603138 Proposition 12 V2 $0 $7,952,824 $0 $0 $7,952,824
2015 CON 019603138 10 - MISCELLANEOUS $35,606,400 $8,901,600 $0 $0 $44,508,000

RTR Project Disbursements

CSJ Total Expenditures
  $31,101,827  
019603138 $31,101,827  
019603248 $0  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2013 ROW 019603138 08/2013 08/2013 12/2017 12/2017
2013 ROW 019603248 08/2013 08/2013 12/2017 12/2017
2013 CON 019603138 08/2013 08/2013 12/2017 12/2017
2015 CON 019603138 08/2013 08/2013 12/2017 12/2017

TIP 53123 Environmental Review Documents

No reports found