TIP Code: | 30000 |
CSJ: | |
County: | DALLAS |
City: | VARIOUS |
Agency: | NCTCOG |
Project Type: | OTHER |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | VA |
Limits (from): | NTTA SIB LOAN PLACEHOLDER FOR PGBT |
Limits (to): | |
Scope of Work: | PLACEHOLDER FOR THE $138M NTTA LOAN; ANNL PMNTS APPLIED TO PRINCIPAL BALANCE UNTIL PAID IN FULL; ACCRUED INTEREST ALLOCATED TO EACH ACCT THROUGH RTR RECLASS UPON FULL REPMNT OF PRINCIPAL LOAN AMNT (ANTICIPATE INTEREST ALLOCATED STARTING FY2025) |
Comments: | PLACEHOLDER FOR THE $138M NTTA LOAN; APPROVED BY TTC IN OCTOBER (MINUTE ORDER 113320); EXPENDITURES OCCURRED IN FEBRUARY 2013 |
Total Project Cost
CSJ | Phase | Total Project Cost |
---|---|---|
Total: | $0 | |
N/A | Implementation | $0 |
N/A | Construction Engineering | $0 |
N/A | Contingencies | $0 |
N/A | Indirect Costs | $0 |
N/A | Bond Financing | $0 |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $0 | $0 | $0 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$0 | $0 |
Status
Fiscal Year | Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|---|
2013 | IMP | 01/2013 | 09/2012 | 01/2029 | 10/2022 |
TIP 30000 Environmental Review Documents
No reports found |
TIP 30000 Project Attachments
No reports found |