Funding :: DALLAS :: Project 20265 Details

TIP Code: 20265
CSJ: 0009-11-226
County: DALLAS
City: DALLAS
Agency: TXDOT-DALLAS
Project Type: INTERCHANGE
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: IH 30
Limits (from): IH 35E INTERCHANGE
Limits (to): WEST OF IH 45 INTERCHANGE
Scope of Work: RECONSTRUCT INTERCHANGE WITH 5 MAIN LANES, 6 COLLECTOR DISTRIBUTOR ROADS, AND OPERATIONAL IMPROVEMENTS
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $117,785,899
000911226 Engineering $2,500,000
000911226 Construction $113,935,899
000911226 Construction Engineering $1,350,000
000911226 Contingencies $0
000911226 Indirect Costs $0
000911226 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $74,508,720 $41,927,179 $0 $0 $116,435,899
2011 ENG 000911226 Proposition 12 V2 $2,000,000 $500,000 $0 $0 $2,500,000
2013 CON 000911226 12 ( S ) $3,560,000 $890,000 $0 $0 $4,450,000
2013 CON 000911226 Proposition 12 V1 $0 $10,000,000 $0 $0 $10,000,000
2013 CON 000911226 Proposition 12 V2 $68,948,720 $17,237,179 $0 $0 $86,185,899
2013 CON 000911226 Proposition 14 $0 $13,300,000 $0 $0 $13,300,000

RTR Project Disbursements

CSJ Total Expenditures
  $0  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2011 ENG 000911226 03/2013 03/2011 08/2017 08/2017
2013 CON 000911226 03/2013 03/2013 08/2017 08/2017